KAEFER Thailand received the order for thermal insulation on RRC Upgrade Project from SKEC. The work involves thermal insulation of equipment(including towers) and piping. The scope also includes scaffolding required for insulation.
Earlier K-Th had already received order for refractory work on the same project, which is now 85% successfully completed.
This order is strategically important to us as our target is always to get repeat orders from our regular clients. Since we did ATC1 expansion project for SKEC in year 2005, we have worked with them on all their projects involving insulation, scaffolding and refractory.
Congratulations to Drapan and his team.
Project Management Department headed by Ravindran shall lead this project with Nitin as Site Incharge.
SB